What Happens If a Builder Does Not Register a Project Under RERA
The Real Estate (Regulation and Development) Act, 2016 (RERA) was introduced to bring greater transparency, accountability and protection to India's real estate sector. It establishes rules that developers and promoters must follow when developing and selling eligible real estate projects.
One of the most important requirements under RERA is mandatory project registration before advertising, marketing, booking or selling units in a project covered by the Act.
But what happens if a builder starts selling apartments without obtaining RERA registration? Can the developer face penalties? Can homebuyers take legal action? And what should buyers do if they discover that their project is not registered?
In this guide, we explain the legal consequences of non-registration, penalties under the RERA Act, homebuyer rights and the steps developers should take to remain compliant.
1. Is RERA Registration Mandatory for Builders?
Yes. Under Section 3 of the RERA Act, 2016, a promoter cannot advertise, market, book, sell, offer for sale or invite people to purchase plots, apartments or buildings in a real estate project requiring registration without first registering the project with the respective State RERA Authority.
For example, a developer launching a residential project in Maharashtra must obtain registration from MahaRERA, provided the project falls within the scope of the Act and does not qualify for an exemption.
The registration requirement applies to eligible residential, commercial and mixed-use real estate projects.
It is important to understand that obtaining local authority approvals and obtaining RERA registration are separate requirements. Having building permissions does not automatically exempt a project from RERA registration.
2. What Happens If a Builder Does Not Register a Project Under RERA?
If a promoter fails to register a project that is legally required to be registered, the consequences can be serious.
The RERA Act provides specific penalties and regulatory powers to address non-compliance.
A. Penalty of Up to 10% of the Estimated Project Cost
Under Section 59(1) of the RERA Act, a promoter who violates Section 3 by failing to register an eligible project may face a penalty of up to 10% of the estimated cost of the real estate project, as determined by the Regulatory Authority.
For example:
If the estimated cost of a project is ₹50 crore, the maximum penalty under Section 59(1) could be:
₹50 crore × 10% = ₹5 crore.
The actual penalty is determined by the Regulatory Authority. It is not automatically 10% in every case.
B. Imprisonment of Up to Three Years
The consequences can become more serious if the promoter continues violating the registration requirement or fails to comply with the Authority's orders, decisions or directions.
Under Section 59(2), the promoter may face:
Imprisonment for a term of up to three years.
A fine of up to a further 10% of the estimated project cost.
Both imprisonment and fine.
These consequences arise under the conditions specified in Section 59(2), rather than automatically applying to every instance of non-registration.
C. Regulatory Action Against the Project
The Regulatory Authority has powers to investigate violations and take appropriate action under the Act.
In Maharashtra, MahaRERA can initiate suo motu action against a promoter for non-registration, even when no homebuyer has filed a complaint.
Depending on the circumstances, the Authority may issue directions and take further action in accordance with the Act.
D. Restrictions on Advertising and Selling
A builder cannot legally continue advertising, marketing, booking or selling units in an eligible project without obtaining the required registration.
This means promotional activities, property advertisements, sales campaigns and booking activities can create regulatory exposure if the project has not been registered.
Developers should obtain the registration number before starting marketing and sales activities.
3. Which Projects Are Exempt from RERA Registration?
Not every real estate project requires RERA registration. Section 3(2) of the Act provides certain exemptions.
A project may not require registration under the central Act in the following circumstances:
1. Small projects
Where the area of land proposed to be developed does not exceed 500 square metres OR the number of apartments proposed to be developed does not exceed eight, inclusive of all phases.
The appropriate State Government may reduce these thresholds.
2. Projects with an earlier completion certificate
Where the promoter received a completion certificate for the real estate project before the commencement of the RERA Act.
3. Renovation or redevelopment projects
Projects involving renovation, repair or redevelopment that do not involve marketing, advertising, selling or new allotment of any apartment, plot or building.
Important: The exemption criteria must be assessed carefully under the applicable state rules and notifications. A project should not be treated as exempt merely because the developer assumes it falls below a particular threshold.
Also, where a project is developed in phases, each phase is treated as a standalone real estate project and generally requires separate registration unless an exemption applies.
4. What Can Homebuyers Do If a Builder Has Not Registered the Project?
Homebuyers should verify the project's registration status before making payments or signing an agreement.
If a buyer discovers that an eligible project is being marketed or sold without registration, the following steps can help.
Step 1: Verify the Project Registration Status
Visit the official website of the respective State RERA Authority and search for the project using its name, promoter details or location.
For Maharashtra, buyers can use the official MahaRERA website:
https://maharera.maharashtra.gov.in/
Step 2: Collect Relevant Documents
Keep copies of relevant records, including:
Booking forms and payment receipts.
Builder advertisements and promotional material.
Brochures and project details.
Emails, messages and communication with the developer.
Any agreement or document signed with the promoter.
These records may help establish the facts and support a complaint.
Step 3: Raise the Issue with the RERA Authority
An affected buyer can approach the appropriate RERA Authority and seek guidance on the available remedies.
Section 31 of the RERA Act provides a mechanism for filing complaints before the Authority or adjudicating officer, as applicable.
The correct forum and remedy depend on the nature of the violation and the relief being sought.
Step 4: Seek Legal Advice
If money has been paid or the developer has made misleading representations, buyers should consider consulting a qualified legal professional to understand their options under RERA and other applicable laws.
5. What Are the Rights of Homebuyers Under RERA?
RERA provides several protections to homebuyers dealing with registered projects and other matters falling within its scope.
Some important protections include:
Right to project information: Buyers can access project registration details and disclosures available on the relevant RERA portal.
Right to timely possession: Section 18 provides remedies in specified circumstances where a promoter fails to complete or give possession in accordance with the agreement for sale.
Right to claim a refund or interest: Depending on the circumstances, an allottee may be entitled to a refund with interest or interest for delay, as provided under Section 18.
Right to raise complaints: Under Section 31, an aggrieved person can file a complaint for violations of the Act, rules or regulations.
Right to information: Buyers can check relevant project details, approvals, declared completion timelines and other information disclosed by the promoter.
The availability of a particular remedy depends on the facts, the applicable provisions and the nature of the project.
6. Can a Builder Sell Flats Without a RERA Registration Number?
A promoter cannot advertise, market, book, sell or offer for sale units in a project that requires RERA registration without first obtaining registration.
The registration number must also be included in project advertisements and promotional materials in accordance with the applicable requirements.
If a developer claims that registration is not required, buyers should verify the exemption rather than relying only on verbal assurances.
7. What Should Builders Do to Avoid RERA Non-Compliance?
Developers can reduce regulatory risks by completing the necessary compliance steps before launching a project.
Here are some important measures:
Check whether the project falls under the RERA registration requirement.
Identify the correct State RERA Authority.
Obtain the required planning and building approvals.
Prepare the necessary project documents and promoter declarations.
Submit the registration application with accurate information.
Obtain the RERA registration number before beginning marketing or sales.
Keep project disclosures and periodic updates accurate and current.
Monitor registration validity and apply for an extension wherever required.
Following these steps can help developers avoid unnecessary regulatory complications and maintain transparency with prospective buyers.
8. How Does MahaRERA Handle Projects That Are Not Registered?
In Maharashtra, MahaRERA regulates eligible real estate projects under the RERA Act and the Maharashtra RERA Rules.
Promoters must register eligible projects before advertising, marketing, booking or selling units.
MahaRERA's published FAQs clarify that the Authority can initiate suo motu action where a builder has not registered a project, even if no one has filed a complaint.
This makes it important for developers to review their registration obligations before launching a project.
Developers operating in Maharashtra should regularly refer to the official MahaRERA portal for registration requirements, orders, circulars and regulatory updates.
Official website: https://maharera.maharashtra.gov.in/
9. How RERA Vision Helps Developers Stay Compliant
RERA compliance involves several stages, from checking registration eligibility and preparing documentation to submitting applications and maintaining project disclosures.
At RERA Vision, we assist real estate developers with regulatory and compliance-related requirements, helping them navigate the MahaRERA process with greater clarity.
Our services include:
New MahaRERA project registration.
Project extension applications.
Correction and modification applications.
Documentation and application support.
Ongoing RERA compliance guidance.
Assistance with regulatory requirements and updates.
Our objective is to help developers understand their compliance responsibilities and manage their RERA-related processes more effectively.
Final Thoughts
Not registering an eligible real estate project under RERA can expose a builder to significant financial and legal consequences.
Under Section 59 of the RERA Act, 2016, non-registration can attract a penalty of up to 10% of the estimated project cost. Continued violation or failure to comply with the Authority's directions can lead to further penalties, including imprisonment of up to three years.
For homebuyers, checking the RERA registration status before booking a property is an important step towards making an informed decision.
For developers, completing registration before advertising or selling units is essential to maintaining regulatory compliance and building buyer confidence.
Need assistance with MahaRERA registration or project compliance? Connect with RERA Vision for professional guidance.
Frequently Asked Questions: What Happens If a Builder Does Not Register a Project Under RERA?
1. Is RERA registration mandatory for all builders in India?
RERA registration is mandatory for promoters developing real estate projects that fall within the registration requirements of Section 3 of the RERA Act, 2016. Certain projects may qualify for exemptions under the Act.
2. What happens if a builder does not register a project under RERA?
If a builder fails to register an eligible project, the RERA Authority can impose penalties under Section 59 of the RERA Act. The builder may also face further legal consequences for continued violations.
3. What is the penalty for not registering a project under RERA?
Under Section 59(1), a promoter who violates the registration requirement may face a penalty of up to 10% of the estimated cost of the real estate project, as determined by the Regulatory Authority.
4. Can a builder go to jail for not registering a project under RERA?
Yes. Under Section 59(2), continued violation of Section 3 or failure to comply with the Authority's orders can result in imprisonment of up to three years, a fine of up to a further 10% of the estimated project cost, or both.
5. Can a builder sell flats without a RERA registration number?
No. A promoter cannot advertise, market, book, sell or offer units for sale in a project requiring RERA registration without obtaining registration from the respective State RERA Authority.
6. Which projects are exempt from RERA registration?
Under Section 3(2), exemptions include projects where the land area does not exceed 500 square metres or the number of apartments does not exceed eight, inclusive of all phases; projects that received a completion certificate before the commencement of RERA; and certain renovation or redevelopment projects without new marketing, sale or allotment. State governments may reduce the prescribed thresholds.
7. Can a homebuyer file a complaint against a builder for not registering a project?
An aggrieved homebuyer can approach the appropriate RERA Authority under Section 31 of the Act, depending on the nature of the violation and the relief sought. Buyers should keep relevant payment records, advertisements and communications as supporting evidence.
8. Can MahaRERA take action against a builder without a homebuyer complaint?
Yes. MahaRERA can initiate suo motu action against a promoter for failing to register an eligible project, even if no homebuyer has filed a complaint.
9. How can I check whether a builder's project is RERA registered?
Visit the official website of the respective State RERA Authority and search using the project name, promoter name or registration number. In Maharashtra, buyers can verify project details through the official MahaRERA website.
10. What rights do homebuyers have if a builder violates RERA rules?
Homebuyers can seek appropriate remedies under the RERA Act, including filing complaints under Section 31. Depending on the circumstances, they may also claim refund, interest or compensation under the relevant provisions.
11. Is RERA registration required for commercial projects?
Yes. Eligible commercial real estate projects, including offices and shops, generally require RERA registration unless they qualify for an exemption under the Act.
12. Does RERA registration apply separately to each project phase?
Yes. Under the RERA Act, each phase of a real estate project is treated as a standalone project and generally requires separate registration, subject to applicable exemptions.
13. Can a builder advertise a project before obtaining RERA registration?
No. Under Section 3, a promoter cannot advertise, market, book, sell or offer units in an eligible project before obtaining the required RERA registration.